Putting money where it returns, spending it in the right order, and putting the work on record. No commission from yards, no materials sold.⁠⁠‍​‌‍​‌​⁠‍​‌‌‍‍⁠​​‍‌‌​

A refit is not about making a boat new. It is about putting money where it returns. The same budget creates value on one boat and simply disappears on another. The difference lies in what is established before work starts, and in the order the work is done.

This page sets out what an independent supervisor does during a refit, which decisions must be made in which order, and where budgets leak. We take no side in the choice of yard, the scope or the payment plan: we take no commission from yards and we sell no materials.

1. The Refit Decision: Three Questions First

1. Is the boat worth it? If the market value after the refit is lower than today's value plus the cost of the work, you are not investing, you are spending. This calculation is arithmetic, not sentiment. On some boats the right answer is "sell this one and put the budget into a bigger boat", and saying so is part of the job.

2. Is the structure sound? If the shell, the keel attachment, the hull-to-deck joint and the main bulkheads are sound, it is worth investing on top of them. If any of those four is compromised, they come first. Galley and upholstery come later.

3. How much will you actually use her? A full refit rarely makes sense on a boat used two weeks a year. Intensity of use decides which systems are worth renewing.

2. The Right Order

The most expensive mistake in a refit is doing things out of sequence. Discovering a deck leak after the new upholstery is fitted means paying for the same work twice. The order is:

#StageWhy here
1Structure and watertightnessHull, deck, keel attachment, chainplates, windows and hatches. Until water ingress is solved, nothing done inside will last.
2System infrastructureWiring, fuel lines, raw water circuit, bilge and bonding. These disappear behind linings; reaching them later means dismantling.
3Main engine and driveEngine, shaft line, propeller, controls. If the engine must come out, it comes out before interior work.
4Rig and deck gearIf the mast is coming down, it is timed to coincide with paint and deck work.
5Paint and surfacesAntifouling, topsides, deck covering, after the structural work is finished.
6Interior and comfortUpholstery, joinery, galley, electronics. Last, because all of it is visible surface and the earlier stages would damage it.

3. What an Independent Supervisor Does

Refit consultancy is not about getting work done at a yard. It is about putting the work that was done on record. The role covers:

Independence: we do not sell repair work on a boat we have surveyed and we take no commission from yards. If you ask for a yard recommendation you get several names and we are paid by none of them. That rule is the only thing that makes the report worth anything.

4. Where Budgets Leak

LeakWhy it happensHow it is prevented
Out-of-scope work"While we're in there, let's also…", extras can reach a third of the budgetWritten approval and price for every addition; no verbal decisions
Hidden damage found lateRot, corrosion or delamination revealed once panels come offMeasurement at the baseline stage; a 15-20% contingency in the budget
Incompatible materialsDifferent resin, different metal, different coating, adhesion and galvanic problemsMaterial decisions in writing, verified against technical data sheets
WorkmanshipCorners cut where nobody will lookStage inspection before anything is closed up
Schedule slipHardstanding, crane and marina costs run on with the workA delay clause in the contract; a critical-path plan
Missing documentationNo record of the work, it creates no value at resalePhotographs and invoices filed per stage; a complete file at handover

5. Material by Material

GRP / fibreglass

The most common refit subjects are osmosis and delamination. In osmosis repair the decisive factor is drying time: once the gelcoat is peeled, the laminate takes weeks to dry, and no new coating goes on until moisture readings confirm it. An osmosis repair closed too early returns within two seasons. In structural reinforcement, resin compatibility matters: epoxy bonds over polyester, the reverse is not reliable.

Steel

Plate thickness sits at the centre of any steel refit. Ultrasonic readings are taken on a grid and compared with original scantlings. Where local wastage passes the threshold, the answer is plate renewal rather than a patch. Corrosion resistance changes in the heat-affected zone after welding; surface preparation and the coating system matter as much as the weld itself. Spaces that cannot be reached from inside, deep tanks, under the bilge, are the riskiest part of a steel refit.

Aluminium

Welding aluminium is a different discipline from steel and demands control of heat input. The real risk is galvanic: wherever dissimilar metals, stainless fastenings, bronze valves, meet an aluminium hull, isolation is mandatory. Every new metal component added during a refit changes the cathodic balance, so the anode plan is recalculated at the end of the job.⁠⁠‍​‌‍​‌​⁠‍​‌‌‍‍⁠​​‍‌‌​

Wood

The material where most is done wrong. The common errors: patching with a different species, sealing damp timber under epoxy, the wrong compound in a caulking seam, and cosmetic repair without renewing fastenings. On a wooden boat, work starts at the fastenings, not at the visible surface. Sealing wet timber with epoxy accelerates decay, because the moisture stays inside.

6. New-Build Consultancy

Commissioning a new boat carries a different risk from buying an existing one: you pay before you see the product. By the time the boat exists, the money is spent. That is why supervision matters more in a new build than in a refit.

Contract stage

Stage inspections

StageWhat is checked
Materials inCertificates for resin, fabric, plate or timber; specification checked against technical data sheets
Mould and laminationPly sequence, thickness readings, cure conditions; on metal hulls, plate thickness and weld runs
StructureBulkhead bonding, keel seating, engine beds, hull-to-deck joint, before anything is closed
SystemsCable sizing and protection, fuel line material, raw water circuit, bonding, before linings go on
MachineryAlignment, flexible mounts, exhaust run, cooling circuit
Before launchAll seacocks, shaft seal, anode layout, watertightness test
Sea trialStaged load, temperatures, vibration, steering behaviour, system readings under electrical load
HandoverSnag list, document file, warranty start, familiarisation
Note: every stage inspection closes with a written report and a photograph file. That file is the single most valuable document a boat carries through her life, it is the first thing a buyer will ask for.

7. Realistic Timescales

None of these figures mean anything unless they are in the contract. A build contract without a timetable is a commitment of unspecified duration.⁠⁠‍​‌‍​‌​⁠‍​‌‌‍‍⁠​​‍‌‌​

Frequently Asked Questions

This is arithmetic, not sentiment: if today's value plus the cost of the refit exceeds the market value afterwards, you are spending rather than investing. After the structural assessment we work that calculation out with you, and if the answer is 'sell', we say so.
We give several names and take commission from none of them. The choice is yours; our job is to record the work done at the yard you choose.
It depends on scope. The critical moments are known: before laminate is closed, before wiring disappears behind a lining, before the engine sits on its beds, before launch. A limited refit typically needs 3-4 visits, a full refit 8-12. The visit plan goes into the contract.
Because at the end of the job the question 'was that damage already there?' always arises. A measured, photographed baseline report ends that argument before it starts, and it protects the yard as much as it protects you.
Tie them to stages rather than dates: hull out of mould, deck joined, engine installed, launch, handover. Write a condition of independent verification into each stage. A front-loaded payment plan increases your risk, not the yard's.
Not necessarily, but it demands more craft and returns faster when done wrong. On a wooden boat the work starts at the fastenings, not the visible surface; any repair that skips that order is cosmetic.
If it is documented, yes. Work without invoices and photographs effectively does not exist for a buyer. What creates value is the record as much as the work.
Have it stated explicitly in the contract. Who carries the fire and damage risk at the yard, at what stage title passes, and what the cover includes should all be unambiguous.

Related Pages

Let us work out your refit decision together

Tell us about the boat and the plan; we will see together whether it is an investment or an expense.

💬 WhatsApp 📝 Written quote 📞 +90 501 5 SURVEY

Request a Survey Online

Fill in the form and we will come back with an itemised written quotation.