You pay before you see the product. That is why supervision matters more here than in a refit, and why every late inspection ends up behind a closed laminate.⁠⁠‍​‌​​‍​‌‍‍‍‍​​‍‍​‍​​‌

Commissioning a new boat carries a different risk from buying an existing one: you pay before you see the product. By the time the boat exists, the money is spent.

Where we stand: we are there on your behalf, not alongside the yard. We take no commission and sell no materials. The job is to verify compliance with the specification and to put the process on record.

1. Contract Stage: the Cheapest Place to Intervene

The most valuable work in a new build happens before signature. Everything corrected afterwards is expensive.

Technical specification

The specification is the heart of the contract, and it belongs at make-and-model level. "Quality generator" is not a specification; make, model, output, quantity and location is. It should cover:

Payment plan

Tied to stages, not dates: hull out of mould, deck joined, engine installed, launch, handover. A condition of independent verification at each stage goes into the contract, that stage's payment follows verification. A front-loaded plan increases your risk, not the yard's.⁠⁠‍​‌​​‍​‌‍‍‍‍​​‍‍​‍​​‌

Other essential clauses

2. Stage Inspections

StageWhat is checked
Materials inCertificates for resin, fabric, plate, profile or timber; batch numbers; data sheets compared with the specification; storage conditions and shelf life
Mould and laminationPly sequence and orientation, thickness readings, resin-to-glass ratio, cure conditions (temperature and humidity logged), vacuum records where infusion is used, core placement and bonding
Welding on metal hullsWelding procedure (WPS) and welder qualification, visual weld inspection, non-destructive testing (NDT) coordinated with an accredited provider where required, distortion control, plate thickness verification
StructureBulkhead bonding and tabbing widths, keel seating and bolt arrangement, engine beds, hull-to-deck joint, before anything closes
SystemsCable sizing and colour coding, protective devices, fuel line material and venting, raw water circuit and seacocks, bonding continuity, sealing at bulkhead penetrations, before linings
Weight trackingWeight recorded stage by stage against the contract commitment. Excess weight permanently spoils trim, draft and performance and cannot be corrected later.
MachineryAlignment readings, flexible mounts, exhaust run and waterlock, cooling circuit, control cables
Paint and finishSurface preparation, coat count, dry film thickness readings, application conditions (temperature, humidity, dew point)
Before launchAll seacocks, shaft seal, anode layout and bonding, watertightness test, trim and stability check
Sea trialStaged load, temperatures, vibration, maximum and cruising speed, fuel consumption, steering behaviour, system readings under electrical load, noise levels
HandoverSnag list, document file, warranty start, familiarisation, spares and keys
The two inspections skipped most often: weight tracking and the check before linings close. The first surfaces at handover and cannot be fixed; the second returns years later as a fault, and by then a lining has to come off.

3. Snag List and Handover

Handover is a process, not a signature. How it should work:

  1. A thorough pre-handover inspection and a numbered snag list, each item photographed and defined.
  2. Agreement with the yard on the list: what is rectified before handover, what falls under warranty.
  3. The balance payment tied to completion of the pre-handover items.
  4. The warranty period starting at actual handover, not earlier on paper.
  5. Complete delivery of the document file: certificates, data sheets, schematics, manuals, warranty documents, stage photographs.

4. The Document File

The file assembled during construction is the most valuable document the boat carries through her life: material certificates and batch numbers, lamination or welding records, stage inspection reports and photographs, weight records, paint system and film thickness readings, system schematics, sea trial measurements, the snag list and its closure.

Without it, ten years on, the boat is "an unknown build" to a buyer. With it, she is a boat whose every stage was verified, and the difference goes straight into the price.⁠⁠‍​‌​​‍​‌‍‍‍‍​​‍‍​‍​​‌

5. Realistic Timescales

A build contract without a timetable is a commitment of unspecified duration.

Frequently Asked Questions

Before the contract is signed. The most valuable point of intervention is when the specification is written; everything corrected later is expensive.
On a one-off build, typically 10-20. What matters is not the number but the timing: the critical moments are the ones before things close, and those are dated in the contract.
Because it surfaces at handover and cannot be corrected. Excess weight permanently spoils trim, draft, performance and fuel consumption, and without stage-by-stage records nobody notices until it is too late.
By stage: hull out of mould, deck joined, engine installed, launch, handover. Write a condition of independent verification into each.
A yard's inspection assesses its own work. Independent supervision does not replace it; the two are meaningful together. A second pair of eyes protects the yard too, by preventing later disputes.
Agreement on a numbered, photographed snag list, the balance payment tied to the pre-handover items, and complete delivery of the document file.
A welding procedure specification defines which method, with which parameters and by which qualified welder, will be used on a metal hull. Its absence means weld quality depends on the individual.

Related Pages

Let us talk before you sign the build contract

The most valuable point of intervention is when the specification is written.

💬 WhatsApp 📝 Written quote 📞 +90 501 5 SURVEY

Tools and related pages

Continue with this topic

Request a Survey Online

Fill in the form and we will come back with an itemised written quotation.